Who pays for the sewer lateral in Dana Point, CA

Which part of the pipe is yours

  • Sewer lateral

    Yours all the way to the main, including the fitting where it joins — if certain conditions are met

    Why, and what to do
  • Water service line

    Yours from the meter to your building

    Why, and what to do

If something’s wrong

If a repair needs a permit or an inspection

  • Before work on the pipe · Permit

    Who issues it:
    City of Dana Point Director of Public Works and Engineering Services
    What it covers:
    breaking the surface of any highway or installing a pipe in or under one, which is where the lateral runs to the main

    Dana Point Municipal Code section 14.01.025 makes it unlawful to "dig up, plow up, remove or break the earth, soil, stone, pavement or other surface of, or otherwise injure any highway", or to install a pipe or any other installation "across, upon, in or under any highway without first obtaining a permit therefore from the Director" - the City's Director of Public Works and Engineering Services. Where South Coast Water District collects the sewage, the lateral is the owner's all the way to the main under the street, so this is the permit an owner needs to reach that part of their own pipe. It is the City's permit and applies whichever district collects.

The repair rule in full, with its sources

No rule on file here is specific to selling, buying, remodelling or adding a unit; that does not mean none exists.

Who to call first about the sewer lateral

BelowGrid has no first-call guidance on file from Dana Point about the sewer lateral.

Dana Point: official site(opens in a new tab)The documents this answer is built on

Who is responsible for which part

In Dana Point the sewer lateral is the property owner's to maintain all the way to the main sewer under the street. The City's utilities page says the sewer system in the city "is owned, operated and maintained by the South Coast Water District", and the District's board resolved in March 2000 that "property owners shall be responsible for the maintenance of the sewer lateral line to the point of connection with the District's collector sewer". The District's wastewater page puts it the same way: property owners are responsible for "the entire length of their lateral line from their home or business to where it meets and connects to the sewer main under the street." The District's sewer infographic settles the joint itself: it labels the lateral as the property owner's responsibility and says that includes the connection.

The property owner

What decides which applies

Sources

South Coast Water District Resolution 22-99/00 (Sewer Lateral Maintenance), a policy re sewer lateral maintenance

Checked

What the rules say

Most relevant if you are remodelling or adding a unit

No rule on file here is specific to remodelling or adding a unit; that does not mean none exists.

Also in force here

  • Before work on the pipePermit
    Who issues it:
    City of Dana Point Director of Public Works and Engineering Services
    What it covers:
    breaking the surface of any highway or installing a pipe in or under one, which is where the lateral runs to the main

    Dana Point Municipal Code section 14.01.025 makes it unlawful to "dig up, plow up, remove or break the earth, soil, stone, pavement or other surface of, or otherwise injure any highway", or to install a pipe or any other installation "across, upon, in or under any highway without first obtaining a permit therefore from the Director" - the City's Director of Public Works and Engineering Services. Where South Coast Water District collects the sewage, the lateral is the owner's all the way to the main under the street, so this is the permit an owner needs to reach that part of their own pipe. It is the City's permit and applies whichever district collects.

    What to do: Before digging in the street to reach a sewer lateral, apply to the City of Dana Point for a permit, find out whether the street was paved or resurfaced in the last five years, and give the Director at least 48 hours' notice before work starts. If South Coast Water District collects your sewage, tell it about the repair in advance as well - its board asks owners to give notice before any repair or cleaning of a lateral. Keep the permit papers after the job, because the permittee answers for the patch if it settles.

    In force since · Checked

    Dana Point Municipal Code section 14.01.025, Excavation, Fills, Obstructions Upon or Injury to Highway

What this page cannot tell you

  • No assistance or grant programme has been reviewed for this jurisdiction yet.
  • No sewer service territory has been mapped for this area, so BelowGrid cannot say who serves an individual address.

Who governs and serves this area

Jurisdiction
Dana Point (municipality)
Sewer service
No map of sewer providers is held here. BelowGrid cannot say which sewer provider serves an individual address.

Look up a specific address

This page describes what applies to properties in Dana Point in general. To see which authorities serve one address, and what records exist for it, search for it.

Search for an address