Skip to main content
BelowGrid

Who pays for the sewer lateral in Union City, CA

Which part of the pipe is yours

If something’s wrong

If a repair needs a permit or an inspection

  • Before work on the pipe · Permit

    Who issues it:
    City of Union City
    What it covers:
    construction or improvements in the public right-of-way

    Union Sanitary District states that where "a sewer lateral repair involves digging in a street or other public right-of-way, an encroachment permit will also be required" from "the agency that maintains the street". In Union City that is the City, and its encroachment permit asks for a completed application, plans of work, a certificate of insurance "for applicant and all subcontractors", a traffic control plan - "site-specific plan required for work on arterial roads", with federal MUTCD typical applications "acceptable for residential needs" - and a "Faithful Performance Bond in the amount of 110% of the estimated cost of work ... due before permit issuance".

  • Before work on the pipe · Permit · Union Sanitary District

    Who issues it:
    Union Sanitary District
    What it covers:
    any work before it begins, including repairs on private property

    "before any work is begun, a USD repair permit is required (even for repairs on private property)". It adds that "if a sewer lateral repair involves digging in a street or other public right-of-way, an encroachment permit will also be required", and that those "are available from the agency that maintains the street. In most cases, this is the city".

The repair rules in full, with their sources

Buying or selling?

No rule on file here is specific to selling or buying; that does not mean none exists.

Planning work?

  • When you remodel · Permit · Union Sanitary District

    An accessory dwelling unit can bring a sewer capacity charge with it here, and the line is drawn by floor area. Union Sanitary District's capacity charge for an ADU "applies to detached ADUs or ADUs that expand a primary residence in excess of 150 square feet", and it states the other side of the line in the same breath: "no capacity charges shall be levied on ADUs within the living area of an existing single family home or ADUs that do not expand the existing residential structure by more than 150 square feet".

  • Before work on the pipe · Permit · Union Sanitary District

    Who issues it:
    Union Sanitary District
    What it covers:
    demolishing a building served by the sewer, and capping or abandoning the lateral that served it

    Knocking a building down here needs the District's permission before the city will give you its own. Union Sanitary District states that "in order to obtain a demolition permit from the cities of Fremont, Newark or Union City, you will be required to obtain a Demolition/Sewer Capping Permit from Union Sanitary District". The reason is the pipe left behind: the District's inspector "will verify that the lateral is properly capped", and it requires capping "so that debris will not get into our sewer lines".

The remodelling rules in full, with their sources

Who to call first about the sewer lateral

BelowGrid has no first-call guidance on file from Union Sanitary District about the sewer lateral.

Union Sanitary District: official site(opens in a new tab)The documents this answer is built on

Who is responsible for which part

The property owner is responsible for the whole lateral, including the run beneath the pavement and the road, up to the point it joins the public main. The District's ordinance goes further than its web page and says the building sewer is owned by the property owner, not merely their responsibility. On a private street or driveway the sewer main itself can be private too, in which case somebody other than the District maintains that as well.

The property owner

What else is worth knowing

Sources

Union Sanitary District, Sewer Repairs

Checked

What the rules say

Some of these requirements are issued by Union Sanitary District rather than by Union City.

Most relevant if you are remodelling or adding a unit

  • When you remodelPermit

    An accessory dwelling unit can bring a sewer capacity charge with it here, and the line is drawn by floor area. Union Sanitary District's capacity charge for an ADU "applies to detached ADUs or ADUs that expand a primary residence in excess of 150 square feet", and it states the other side of the line in the same breath: "no capacity charges shall be levied on ADUs within the living area of an existing single family home or ADUs that do not expand the existing residential structure by more than 150 square feet".

    What to do: Settle the floor area before the drawings are final, because 150 square feet is the whole difference between a capacity charge and none. Ask the District for the current charge - it is set by ordinance and revised, so the figure on an old page is not reliable. Get the city building permit first, then the District's sewer permit, and allow the 24 hours' notice before the sewer work starts. Note the District's own pages give 24 hours in one place and 48 in another, so confirm which applies to your job.

    Issued by Union Sanitary District · In force since · Checked

    Union Sanitary District, Capacity Fees
  • Before work on the pipePermit
    Who issues it:
    Union Sanitary District
    What it covers:
    demolishing a building served by the sewer, and capping or abandoning the lateral that served it

    Knocking a building down here needs the District's permission before the city will give you its own. Union Sanitary District states that "in order to obtain a demolition permit from the cities of Fremont, Newark or Union City, you will be required to obtain a Demolition/Sewer Capping Permit from Union Sanitary District". The reason is the pipe left behind: the District's inspector "will verify that the lateral is properly capped", and it requires capping "so that debris will not get into our sewer lines".

    What to do: Apply to the District before applying to the city, because the city's demolition permit depends on this one. Decide early whether the lateral is being abandoned or kept - if it is being kept, budget for a CCTV survey before reconnection, and ask the District what it will accept as a pass. The capping itself is the owner's contractor's work, not the District's.

    Issued by Union Sanitary District · Checked

    Union Sanitary District, Demolitions

Also in force here

  • Before work on the pipePermit
    Who issues it:
    City of Union City
    What it covers:
    construction or improvements in the public right-of-way

    Union Sanitary District states that where "a sewer lateral repair involves digging in a street or other public right-of-way, an encroachment permit will also be required" from "the agency that maintains the street". In Union City that is the City, and its encroachment permit asks for a completed application, plans of work, a certificate of insurance "for applicant and all subcontractors", a traffic control plan - "site-specific plan required for work on arterial roads", with federal MUTCD typical applications "acceptable for residential needs" - and a "Faithful Performance Bond in the amount of 110% of the estimated cost of work ... due before permit issuance".

    What to do: Ask the City's engineering contact about the bond before accepting a quotation, because the amount follows the estimate and a surety bond takes time to arrange. Confirm whether your street counts as arterial, since that decides whether a traffic control plan has to be drawn for the site. And treat this as the second permit rather than the first: Union Sanitary District requires its own repair permit even for work on private property.

    Checked

    City of Union City, Permits
  • Before work on the pipePermit
    Who issues it:
    Union Sanitary District
    What it covers:
    any work before it begins, including repairs on private property

    "before any work is begun, a USD repair permit is required (even for repairs on private property)". It adds that "if a sewer lateral repair involves digging in a street or other public right-of-way, an encroachment permit will also be required", and that those "are available from the agency that maintains the street. In most cases, this is the city".

    What to do: Get the District's repair permit before work starts, on (510) 477-7500, whichever side of the property line the work is on. If the job reaches the street, ask your city for the encroachment permit as well - the District publishes the numbers: Fremont (510) 494-4700, Newark (510) 578-4589, Union City (510) 675-5305.

    Issued by Union Sanitary District · Checked

    Union Sanitary District, "Sewer Repairs"

What this page cannot tell you

  • No assistance or grant programme has been reviewed for this jurisdiction yet.

Who governs and serves this area

Jurisdiction
Union City (municipality)
Sewer service
  • Union Sanitary District
  • Which provider serves a particular address depends on where it is. Look up an address to resolve it.

Look up a specific address

This page describes what applies to properties in Union City in general. To see which authorities serve one address, and what records exist for it, search for it.

Search for an address