Who pays for the sewer lateral in Reedley, CA

Which part of the pipe is yours

  • Sewer lateral

    Yours all the way to the main under the road

    Why, and what to do
  • Water service line

    Yours from the meter to your building — if certain conditions are met

    Why, and what to do

If something’s wrong

If a repair needs a permit or an inspection

  • Before work on the pipe · Permit

    Who issues it:
    City of Reedley building inspection division, with a separate public works director's permit for work in the right-of-way
    What it covers:
    constructing or replacing a building sewer to the main, and any part of that work in the street

    Reedley City Code section 8-3-2 requires anyone who will "construct a building sewer from a house, commercial or industrial plant, to a main sewer or existing building sewer within a public right of way or public easement" to obtain a permit from the building inspection division, and provides that "Any person performing said construction or any portion thereof within the public right of way or easement shall, in addition, first obtain from the public works director a permit to do so".

The repair rule in full, with its sources

No rule on file here is specific to selling, buying, remodelling or adding a unit; that does not mean none exists.

Who to call first about the sewer lateral

BelowGrid has no first-call guidance on file from Reedley about the sewer lateral.

Reedley: official site(opens in a new tab)The documents this answer is built on

Who is responsible for which part

Reedley puts the building sewer on the owner all the way to the main. Section 8-3-3 provides that "Building sewers between the building drains and the main sewer shall not be considered appurtenances to or part of the main sewer and the responsibility for maintenance of said building sewer shall be that of the owner or person in charge of the premises served by said building sewer."

The property owner

What else is worth knowing

Sources

Reedley City Code section 8-3-3, Plan required

Checked

What is required

  • Before work on the pipePermit
    Who issues it:
    City of Reedley building inspection division, with a separate public works director's permit for work in the right-of-way
    What it covers:
    constructing or replacing a building sewer to the main, and any part of that work in the street

    Reedley City Code section 8-3-2 requires anyone who will "construct a building sewer from a house, commercial or industrial plant, to a main sewer or existing building sewer within a public right of way or public easement" to obtain a permit from the building inspection division, and provides that "Any person performing said construction or any portion thereof within the public right of way or easement shall, in addition, first obtain from the public works director a permit to do so".

    What to do: Before replacing the building sewer, have the contractor obtain both permits, give public works the 24 hours' notice for the connection, and book the inspection before backfilling.

    Checked

    Reedley City Code section 8-3-2, Permit required; fee

What this page cannot tell you

  • No assistance or grant programme has been reviewed for this jurisdiction yet.
  • No sewer service territory has been mapped for this area, so BelowGrid cannot say who serves an individual address.

Who governs and serves this area

Jurisdiction
Reedley (municipality)
Sewer service
No map of sewer providers is held here. BelowGrid cannot say which sewer provider serves an individual address.