Who pays for the sewer lateral in National City, CA

Which part of the pipe is yours

If something’s wrong

If a repair needs a permit or an inspection

  • Any time · Work required

    The length of your line under the street is yours, and the City does the work on it. Section 14.06.050 provides that "All sewer laterals from mains to the property line shall be constructed by the city" and that "All connections to the sewer main in a public street, alley, easement or right-of-way shall be made by the city." Section 14.06.090 adds that no work is done on a connection, "either in the public streets or alleys, or within property lines, until a permit for such construction and work has been issued therefor by the city."

The repair rule in full, with its sources

No rule on file here is specific to selling, buying, remodelling or adding a unit; that does not mean none exists.

Who to call first about the sewer lateral

BelowGrid has no first-call guidance on file from National City about the sewer lateral.

National City: official site(opens in a new tab)The documents this answer is built on

Who is responsible for which part

National City puts the whole line on the owner, with a City service for blockages under the street. Section 14.06.160 provides that "The property owner is responsible for the building connection line from the house to the main", and section 14.06.170 that the building sewer and "the building connection serving such building sewer or drainage piping shall be maintained by the property owner."

The property owner

What else is worth knowing

Sources

National City Municipal Code section 14.06.160, Property owner

Checked

What the rules say

Most relevant if you have a backup or blockage

No rule on file here is specific to a backup or blockage; that does not mean none exists.

Also in force here

  • Any timeWork required

    The length of your line under the street is yours, and the City does the work on it. Section 14.06.050 provides that "All sewer laterals from mains to the property line shall be constructed by the city" and that "All connections to the sewer main in a public street, alley, easement or right-of-way shall be made by the city." Section 14.06.090 adds that no work is done on a connection, "either in the public streets or alleys, or within property lines, until a permit for such construction and work has been issued therefor by the city."

    What to do: Before comparing contractors for a replacement, apply to the director of building and housing for the permit and ask Public Works what it charges to build the street length and how long the wait is. For a blockage, call a licensed plumber first - City crews respond only after one has tried.

    Current wording dates from · Checked

    National City Municipal Code section 14.06.050, Work to be performed by city

What this page cannot tell you

  • No assistance or grant programme has been reviewed for this jurisdiction yet.
  • No sewer service territory has been mapped for this area, so BelowGrid cannot say who serves an individual address.

Who governs and serves this area

Jurisdiction
National City (municipality)
Sewer service
No map of sewer providers is held here. BelowGrid cannot say which sewer provider serves an individual address.

Look up a specific address

This page describes what applies to properties in National City in general. To see which authorities serve one address, and what records exist for it, search for it.

Search for an address