Who pays for the sewer lateral in Huntington Beach, CA

Which part of the pipe is yours

If something’s wrong

If a repair needs a permit or an inspection

  • Before work on the pipe · Permit

    Who issues it:
    City of Huntington Beach
    What it covers:
    installing any pipe, apparatus, appliance or connection to any part of the City sewer system

    "No person shall install any pipe, apparatus, appliance or connection to any part of the City sewer system without first obtaining an encroachment permit to do so. The applicant shall bear the cost for all labor and materials, and shall be a licensed contractor or shall employ a contractor duly licensed under the laws of the State of California to perform such work." A separate clause reaches anyone adding a second home on a lot: where occupancy "is changed from one to two or more ... an additional connection fee shall apply", and the Director "may require the owner of such a parcel of land to install separate sewer lines for each occupancy".

The repair rule in full, with its sources

Buying or selling?

No rule on file here is specific to selling or buying; that does not mean none exists.

Who to call first about the sewer lateral

BelowGrid has no first-call guidance on file from Huntington Beach about the sewer lateral.

Huntington Beach: official site(opens in a new tab)The documents this answer is built on

Who is responsible for which part

The City pays for the run under the road. Huntington Beach Municipal Code § 14.54.035(C) provides that the "City will pay the cost of repair and maintenance of all lateral lines from the City-owned sewer main through the public right-of-way to the private property line", and that "the owner is responsible for all costs of repair and maintenance of all lateral lines on private property not within the public right-of-way". The City took ownership of that portion in January 2008. Your side is the part across your own land.

Huntington Beach
The property owner

What else is worth knowing

Sources

Huntington Beach Municipal Code, Title 14 Water and Sewers, Chapter 14.54 Sewer Service User Charge

Checked

What the rules say

Most relevant if you have a backup or blockage

No rule on file here is specific to a backup or blockage; that does not mean none exists.

Also in force here

  • Before work on the pipePermit
    Who issues it:
    City of Huntington Beach
    What it covers:
    installing any pipe, apparatus, appliance or connection to any part of the City sewer system

    "No person shall install any pipe, apparatus, appliance or connection to any part of the City sewer system without first obtaining an encroachment permit to do so. The applicant shall bear the cost for all labor and materials, and shall be a licensed contractor or shall employ a contractor duly licensed under the laws of the State of California to perform such work." A separate clause reaches anyone adding a second home on a lot: where occupancy "is changed from one to two or more ... an additional connection fee shall apply", and the Director "may require the owner of such a parcel of land to install separate sewer lines for each occupancy".

    What to do: Get the encroachment permit before work is scheduled, and check that whoever quotes the job holds a current California contractor's licence - the code requires it and an unlicensed job is one the City did not permit. Check separately that your contractor and every subcontractor holds a current Huntington Beach business licence, which Title 12 asks for by name, and that their public liability cover meets the City's figure of "$300,000.00 combined single limit per occurrence" with the City named as an additional insured. Agree a completion date with them in writing: the permit "shall be void if the project, including restoration, has not been completed within 60 days", extensions are at the Director's discretion, and overrunning a road or lane closure carries a penalty priced on the public's inconvenience rather than the City's costs - the code says it is "based upon estimated costs to the traveling public due to delays and additional travel distance around roadway closures". If your project adds a dwelling unit, ask Public Works two specific questions early: what the additional connection fee will be, and whether the Director will require a separate sewer line for the new occupancy. Ask before the design is fixed; a second lateral run to the main is not something to discover at plan check. One thing to settle before you need it rather than at the time: if the lateral fails while the department is shut, the code lets the work start, and then gives you four hours. An emergency permit must be applied for "within four hours after the department's offices are first opened", with a written statement of the basis of the emergency and a description of the work done.

    In force since · Checked

    Huntington Beach Municipal Code, Title 14 Water and Sewers, Chapter 14.36 Sewer System Service Connections, Fees, Charges and Deposits

What this page cannot tell you

  • No assistance or grant programme has been reviewed for this jurisdiction yet.
  • No sewer service territory has been mapped for this area, so BelowGrid cannot say who serves an individual address.

Who governs and serves this area

Jurisdiction
Huntington Beach (municipality)
Sewer service
No map of sewer providers is held here. BelowGrid cannot say which sewer provider serves an individual address.

Look up a specific address

This page describes what applies to properties in Huntington Beach in general. To see which authorities serve one address, and what records exist for it, search for it.