Who pays for the sewer lateral in East Bay Regional Private Sewer Lateral Program, CA
Which part of the pipe is yours
Yours all the way to the main under the road — if certain conditions are met
Why, and what to do
If something’s wrong
If a repair needs a permit or an inspection
No rule on file here is specific to a repair; that does not mean none exists.
Buying or selling?
A Compliance Certificate is required to close escrow when a property is sold or transferred. A certificate is valid twenty years after a complete replacement and seven years otherwise.
A 180-day extension is available when buying or selling: if a Compliance Certificate cannot be obtained before title transfers, a Time Extension Certificate allows 180 days for the work, and is valid only when returned with a $4,500 deposit at title transfer.
Planning work?
Where a permit is sought for new construction or for remodelling costing more than $100,000, a Compliance Certificate is required before the final permit or approval is obtained.
Who to call first about the sewer lateral
East Bay Regional Private Sewer Lateral Program: official site(opens in a new tab)The documents this answer is built on
Who is responsible for which part
The property owner is responsible for the entire lateral, upper and lower, from the home to the public main - except in Alameda and Albany, where the programme covers the upper lateral only.
- The property owner
- The programme states that "the property owner is responsible for the entire PSL from their home to the public sewer main (upper and lower lateral), with the exception of Alameda and Albany where the responsibility ends at the property line or curbside cleanout (i.e. upper lateral only)", and describes the same span again as "the entire lateral from the building cleanout to the public sewer main under the street". So in Oakland, Emeryville and Piedmont the run beneath the road is the owner's. In Alameda and Albany the programme reaches the upper lateral only. Both of those cities have answered the rest themselves and the answer is in your favour - see below.
What decides which applies
Sources
East Bay Regional Private Sewer Lateral Program, Frequently Asked QuestionsWhat the rules say
Most relevant if you have received a notice from the city or district
No rule on file here is specific to a notice from the city or district; that does not mean none exists.
Also in force here
Where a permit is sought for new construction or for remodelling costing more than $100,000, a Compliance Certificate is required before the final permit or approval is obtained.
What to do: Check whether a current certificate or exemption already covers this property through the East Bay Regional Private Sewer Lateral Program before planning the permit timeline around an inspection.
Consolidated Regional Private Sewer Lateral Ordinance, effective 24 May 2019Why this matters
This is the highest threshold of the covered programmes - Berkeley's own ordinance, which this one does not cover, fires at $60,000, and three Marin districts at $50,000. It is also required later in the process than its neighbours demand: the certificate is needed before final approval rather than before the permit is issued. A certificate is valid twenty years after a complete replacement and seven years otherwise, and an exemption may be available where the lateral was fully replaced within the last ten years.
A Compliance Certificate is required to close escrow when a property is sold or transferred. A certificate is valid twenty years after a complete replacement and seven years otherwise.
What to do: Check whether a current certificate or exemption already covers this property through the East Bay Regional Private Sewer Lateral Program before arranging an inspection.
Consolidated Regional Private Sewer Lateral Ordinance, effective May 24, 2019Why this matters
An exemption may be available if the sewer lateral was fully replaced within the last ten years, or if an unexpired certificate from another agency already covers the property. Whether one already exists is not something an address lookup can answer - ask the programme, which holds the certificate records.
A 180-day extension is available when buying or selling: if a Compliance Certificate cannot be obtained before title transfers, a Time Extension Certificate allows 180 days for the work, and is valid only when returned with a $4,500 deposit at title transfer.
What to do: If the lateral cannot be certified before completion, ask the East Bay Regional Private Sewer Lateral Program about a Time Extension Certificate, and agree in writing which party will receive the $4,500 refund.
East Bay Regional Private Sewer Lateral ProgramWhy this matters
The certificate requirement reads as an absolute bar on closing escrow, and it is not one. The $4,500 is a deposit rather than a fee - the programme states it "will be released to the designated party when compliance is achieved" and is refunded if compliance is met within the 180 days - but it still has to be found at title transfer, and the Time Extension Certificate itself carries its own charge.
What this page cannot tell you
- No assistance or grant programme has been reviewed for this jurisdiction yet.
- BelowGrid holds no separate map of sewer providers here. This page gives East Bay Regional Private Sewer Lateral Program's own answer, for the area inside the boundary BelowGrid holds for it; look up an address to see whose answer applies there.
Who governs and serves this area
- Jurisdiction
- East Bay Regional Private Sewer Lateral Program (special district)
- Sewer service
- No separate map of sewer providers is held here. This page gives East Bay Regional Private Sewer Lateral Program’s own answer, for the area inside the boundary BelowGrid holds for it. Look up an address to see whose answer applies there, or check the name on your sewer bill.
Where else this answer applies
The same authorities settle this in the places below too:
Each of them gets its answer from the same authorities.
How this compares to neighbouring districts
3 of the 4 nearest districts draw the line somewhere else. Each authority publishes only its own rule.
Nearby districts and further reading
Look up a specific address
This page describes what applies to properties in East Bay Regional Private Sewer Lateral Program in general. To see which authorities serve one address, and what records exist for it, search for it.
Search for an address