Who pays for the sewer lateral in Lawndale, CA

Which part of the pipe is yours

If something’s wrong

If a repair needs a permit or an inspection

  • Before work on the pipe · Permit

    Who issues it:
    City of Lawndale public works department
    What it covers:
    excavating or disturbing any public street or right-of-way, which is where this city's code puts the lateral

    Lawndale Municipal Code section 12.08.010(A) makes it unlawful "to make or cause to be made any excavations in, upon or under the surface of any public highway in the city, or to dig in, plow up, tear up, fill, cover, disturb or change any portion of the same ... without first obtaining a written permit from the city public works department", and defines a public highway as "any public street, public right-of-way or public place for the purpose of travel". The City's own sewer ordinance puts the lateral under that road on the owner, so this is the permit a Lawndale owner needs to reach their own pipe. Section 12.08.100 then sets how long a new road surface is closed to them: "on a newly paved, constructed, or reconstructed street, the pavement surface shall not be cut or opened for a period of five years", and three years on a slurry sealed street.

The repair rule in full, with its sources

No rule on file here is specific to selling, buying, remodelling or adding a unit; that does not mean none exists.

Who to call first about the sewer lateral

BelowGrid has no first-call guidance on file from Lawndale about the sewer lateral.

Lawndale: official site(opens in a new tab)The documents this answer is built on

Who is responsible for which part

Lawndale writes no sewer ownership rule of its own. Lawndale Municipal Code section 13.04.010 adopts "Title 20, utilities, Division 2, sanitary sewers and industrial waste of the Los Angeles County Code, as adopted, amended and in effect on July 7, 2006" as the City's own sanitary sewer ordinance, and section 13.04.020 swaps the names in it - "county engineer" means the city engineer, "County of Los Angeles" means the city of Lawndale. Inside that adopted division the answer is plain: section 20.24.080 provides that all house laterals "shall be maintained by the owner of the property served in a safe and sanitary condition". What makes it worth reading twice is the division's definition of the thing being maintained. Section 20.20.130 says a "house lateral" is "that part of the sewer piping within the street or right-of-way which extends from the property or sewer right-of-way line to a construction with the main-line sewer" - so the length the code puts on the owner is the length under the road.

The property owner

What else is worth knowing

Sources

Lawndale Municipal Code chapter 13.04, Sanitary Sewer and Industrial Waste Code

Checked

What the rules say

Most relevant if you are repairing or replacing the pipe

  • Before work on the pipePermit
    Who issues it:
    City of Lawndale public works department
    What it covers:
    excavating or disturbing any public street or right-of-way, which is where this city's code puts the lateral

    Lawndale Municipal Code section 12.08.010(A) makes it unlawful "to make or cause to be made any excavations in, upon or under the surface of any public highway in the city, or to dig in, plow up, tear up, fill, cover, disturb or change any portion of the same ... without first obtaining a written permit from the city public works department", and defines a public highway as "any public street, public right-of-way or public place for the purpose of travel". The City's own sewer ordinance puts the lateral under that road on the owner, so this is the permit a Lawndale owner needs to reach their own pipe. Section 12.08.100 then sets how long a new road surface is closed to them: "on a newly paved, constructed, or reconstructed street, the pavement surface shall not be cut or opened for a period of five years", and three years on a slurry sealed street.

    What to do: Ask the public works department two things before accepting a quotation: when the street outside was last paved or slurry sealed, and what bond the city engineer will set. If the street is inside the moratorium, ask what the city engineer needs in order to apply the "no other reasonable means of providing service" exemption. If the work is an emergency, section 12.08.090 allows the excavation without the permit first where it was impractical to obtain one - and fixes the test plainly: "it is feasible to obtain a permit when City Hall is open for business", so an emergency during office hours is not one.

    Current wording dates from · Checked

    Lawndale Municipal Code chapter 12.08, Excavations and Encroachments

What this page cannot tell you

  • No assistance or grant programme has been reviewed for this jurisdiction yet.
  • No sewer service territory has been mapped for this area, so BelowGrid cannot say who serves an individual address.

Who governs and serves this area

Jurisdiction
Lawndale (municipality)
Sewer service
No map of sewer providers is held here. BelowGrid cannot say which sewer provider serves an individual address.

Look up a specific address

This page describes what applies to properties in Lawndale in general. To see which authorities serve one address, and what records exist for it, search for it.

Search for an address