Sewer lateral requirements in Hermosa Beach, CA

Who is responsible for which part of the lateral in Hermosa Beach has not been reviewed yet. What has been reviewed is what applies when you work on one, which is below.

Which part of the pipe is yours

If something’s wrong

If a repair needs a permit or an inspection

  • Before work on the pipe · Permit

    Who issues it:
    City of Hermosa Beach, superintendent of streets
    What it covers:
    excavating a public street, and altering or disturbing street curbing

    Hermosa Beach Municipal Code section 12.12.020 makes it unlawful for any person "to break, lower, remove in any manner, alter or disturb any street curbing" or "to make any excavations in any public street, alley or public place" "without first obtaining a permit so to do from the superintendent of streets". Section 12.09.040 then decides when that permission can be given at all, and the bar is a long one: no excavation in a roadway for three years after roadway maintenance such as a slurry seal, five years after roadway construction such as a grind and overlay, or ten years after the reconstruction of a Portland cement concrete roadway.

  • Before work on the pipe · Permit

    Who issues it:
    City of Hermosa Beach
    What it covers:
    all work in the right-of-way, with sewer lateral connection a named utility permit type

    The City of Hermosa Beach states that "Right of Way permits are required for all work in the right-of-way", and lists "Sewer Lateral Connection" among its Utility Permit categories, marked as requiring inspection. A Right of Way permit needs proof of a State Contractor's License, a City Business License, commercial liability insurance naming the City as additionally insured, and - specifically for Utility permits - both Traffic Control Plans and Work Area Plans. The City asks for applications "a minimum of 1-2 weeks prior to your work commencement". Separately, an ENCROACHMENT permit here is a different thing: it "allows residents or business owners to enter an agreement with the City for on-going private use of the right-of-way", revocable at any time.

The repair rules in full, with their sources

Buying or selling?

No rule on file here is specific to selling or buying; that does not mean none exists.

Planning work?

  • When you remodel · Inspection

    Hermosa Beach adds a section to the California Plumbing Code providing that "the Building Official may require inspection of the private sewer lateral by a licensed plumber using video or equivalent approved methods" in four situations: "a remodel or addition valued at fifty thousand dollars or more is proposed"; "plumbing fixtures are relocated or replaced"; "recurring blockages have occurred"; and where "infiltration, inflow, or structural defects identified in the public sewer indicate possible lateral defects on private property".

The remodelling rule in full, with its sources

Who to call first about the sewer lateral

BelowGrid has no first-call guidance on file for Hermosa Beach about the sewer lateral.

Hermosa Beach: official site(opens in a new tab)

What the rules say

Most relevant if you are selling or buying

No rule on file here is specific to selling or buying; that does not mean none exists.

Also in force here

  • Before work on the pipePermit
    Who issues it:
    City of Hermosa Beach, superintendent of streets
    What it covers:
    excavating a public street, and altering or disturbing street curbing

    Hermosa Beach Municipal Code section 12.12.020 makes it unlawful for any person "to break, lower, remove in any manner, alter or disturb any street curbing" or "to make any excavations in any public street, alley or public place" "without first obtaining a permit so to do from the superintendent of streets". Section 12.09.040 then decides when that permission can be given at all, and the bar is a long one: no excavation in a roadway for three years after roadway maintenance such as a slurry seal, five years after roadway construction such as a grind and overlay, or ten years after the reconstruction of a Portland cement concrete roadway.

    What to do: Before accepting a quotation, ask the Public Works counter when the street outside was last resurfaced or reconstructed and which of the three moratorium periods that starts, because a repair that could wait may have to. Ask for the Pavement Moratorium Guidelines by name - the code makes the exceptions turn on them and does not reproduce them. And ask what deposit the superintendent of streets will set for your length of trench, since it is fixed case by case rather than published.

    In force since · Checked

    Hermosa Beach Municipal Code section 12.12.020, Permit to make street excavations
  • Before work on the pipePermit
    Who issues it:
    City of Hermosa Beach
    What it covers:
    all work in the right-of-way, with sewer lateral connection a named utility permit type

    The City of Hermosa Beach states that "Right of Way permits are required for all work in the right-of-way", and lists "Sewer Lateral Connection" among its Utility Permit categories, marked as requiring inspection. A Right of Way permit needs proof of a State Contractor's License, a City Business License, commercial liability insurance naming the City as additionally insured, and - specifically for Utility permits - both Traffic Control Plans and Work Area Plans. The City asks for applications "a minimum of 1-2 weeks prior to your work commencement". Separately, an ENCROACHMENT permit here is a different thing: it "allows residents or business owners to enter an agreement with the City for on-going private use of the right-of-way", revocable at any time.

    What to do: Apply for a Right of Way permit under Sewer Lateral Connection, not an encroachment permit. Allow one to two weeks, and add three days on top if parking has to be cleared. Check your contractor holds both a State licence and a City business licence and can name the City as additionally insured, and have them price the traffic control and work area plans, which a utility permit requires regardless of disruption.

    Checked

    City of Hermosa Beach, Public Works
  • When you remodelInspection

    Hermosa Beach adds a section to the California Plumbing Code providing that "the Building Official may require inspection of the private sewer lateral by a licensed plumber using video or equivalent approved methods" in four situations: "a remodel or addition valued at fifty thousand dollars or more is proposed"; "plumbing fixtures are relocated or replaced"; "recurring blockages have occurred"; and where "infiltration, inflow, or structural defects identified in the public sewer indicate possible lateral defects on private property".

    What to do: Before a remodel is priced, ask the Building & Safety Division whether a lateral video will be required for the permit, and ask what happens if it finds a defect - the section says who may require the inspection and says nothing about who pays for any repair that follows. Get the answer in writing alongside the plan check.

    In force since · Checked

    Hermosa Beach Municipal Code section 15.12.020, Local amendments to the California Plumbing Code

What this page cannot tell you

  • No assistance or grant programme has been reviewed for this jurisdiction yet.
  • No sewer service territory has been mapped for this area, so BelowGrid cannot say who serves an individual address.

Who governs and serves this area

Jurisdiction
Hermosa Beach (municipality)
Sewer service
No map of sewer providers is held here. BelowGrid cannot say which sewer provider serves an individual address.